Fall 2026 Supply Chain
Supply Chain Analysis
Fuels and Natural Gas
Structural Steel Inputs
Piping
HVAC Equipment
Generators
Electrical Gear
Metals
Concrete and Cement
Insulation
Gypsum and Metal Studs
Lumber and Wood
Supply Chain Analysis
Demand underpins challenges to both project schedules and budgets, with the growth of data center buildouts straining the labor and materials markets, resulting in upward pressure on both materials pricing and lead times. This is being felt the most in the structural steel market—fabricated material pricing is up over 40 percent since the start of the year, and lead times in some markets are now over 60 weeks from approved submittal to ship date. Large-scale generator lead times now consistently exceed 100 weeks. Similarly, increased demand for mineral wool insulation, coupled with manufacturing constraints at Rockwool, have driven lead times from six weeks to 16 weeks over the past year.
Pricing tells a similar story, as the combination of tariffs and the conflict in Iran drive the price of metals and petroleum-based products upward. Increases in petroleum-based product pricing are most visible in roofing materials: since the start of 2026, membrane prices are up 10–15 percent, and polyiso insulation is up 8–12 percent. In addition, delivery surcharges driven by the high cost of diesel fuel are common in many material categories. Copper wire prices are also escalating, and in some markets, copper wire pricing is up more than 25 percent from the start of the year.
Recent changes in tariff policy look to substantially impact the construction industry. As trade tensions mount between the U.S. and Canada, a new steel tariff was implemented by the U.S. on September 15. Fabricated steel imported from Canada is now subject to an additional 50 percent tariff, which stacks on top of existing Section 232 tariffs. Projects in northern states sourcing Canadian steel must now account for tariffs ranging from 60–100 percent.
Lead Times
Note: Skanska currently tracks lead times across 68 different material and equipment categories. Lead times shown do not include submittals and are based on Skanska supplier and regional market data. They may not reflect conditions across the entire industry. Actual lead times vary by market, supplier, and project.